Legendary Concrete Design

Blog

September 2024

Went back out and snapped a couple of pics of our Street of Dreams job from a while back.  Concrete is still looking great.

May June July

Continued construction of foundation.  First we poured the foundation and after it cured we poured the floor for the building.  The project was then finished by others.

April 2024

Site setup for new shop foundation and floor.

January 2024

Finished off pictures of the railing for our job in Lake Oswego.

December 2023

Look how wine cellar turned out, what a beauty!

Oct, Nov, Dec 2023

Installing the stairs, a massive effort over many obstacles! It all comes together!

April-May 2023

Framing the deck and firepit. Pouring the concrete portions of the deck.

January 2023

Shotcrete onto rock wall for a nice textured look.

December 2022

Bombshell foundations for giant stairs from deck.

November 2022

Framing in the wine cellar addition. Starting on the deck build out.  

April 2022

Adding the steel beams for the next level of the addition, and pouring the concrete flooring for the wine cellar.

March 2022

Preparing the floor for the wine cellar concrete pour using vapor barrier and foam insulation, then rebar to strengthen the concrete.

February 2022

Beginning the wine cellar tunnel addition in Lake Oswego.

December 2020

Art installation in Milwaukie made to look like the transit center installation that we helped light up at night by installing the lighting and pouring the concrete to keep it in place.